First 11 of 11 paragraphs shown  Update Reclassification of a Non Credible Contingency Event
 Dederang Glenrowan No.1 and No.3 220kV lines.
 In accordance with the criteria for re-classifying contingency events established under NER clause 4.2.3B, AEMO has declared the simultaneous trip of the following transmission lines as a credible contingency event. Dederang Glenrowan No.1 and No.3 220kV transmission lines as a credible contingency event. Constraint Set: V-DDGN invoked from 1810 hrs until further notice. This Constraint Set contains equations with the following interconnectors on the LHS.
 V-S-MNSP1
 V-SA
 VIC1-NSW1
 The reclassification is continued due to lightning activity.
 Updated advice will be provided at approximately 2300 hrs
 Bruce Fleming
 Power System Operations Manager
   ...Log in to read rest of Article or image.
(2010-02-08)

Please log in to see references.

Article in: [Electricity Week][Energy Daily][EWN Publishing]
Article Tags: [ Energy - Electricity ][ 120kVA up ][ Transmission ][ Lines ][ NEM Electricity Analysis ]


Related Articles
AEMO Notice - Forecast Low Reserve Condition (LRC) in the South Australia Region - 9 February 2010. (08/02/2010) | AEMO Notice - Cancellation - Reclassification of a Non Credible Contingency Event - Eildon Mt. Beauty No.1 and No.2 220kV lines (Vic ) - Lightning Storm.(08/02/2010) | AEMO Notice - Cancellation - Reclassification of a Non Credible Contingency Event - Dederang Glenrowan No.1 and No.3 220kV lines (Vic) - Lightning Storm.(08/02/2010) | One million tonne CO2-3 VEET shortfall revealed |